Tunnel form equipment Prado – Porto

 



Tunnel form equipment Prado – Porto

Customer: UTE Prado-Porto (Vías, Torrescamara, Vimac)
Country: España
Location: Vilar de Barrio (Orense)
Year: 2015

Description:

Construction project for the new HSR called the North-Northwest Corridor. Built by the Ministry of Development through Adif Madrid-Galicia HSR. Puebla de Sanabria-Lubián-Ourense section. Prado-Porto sub-section, single high-speed international gauge track with maximum speeds of 350 km / h. Right track (9.1km.) And left track 1.6 km

IDENTIFIED NEEDS:
Self-supporting equipment consisting of 2 formwork and 2 transfer travelers, R = 4.38 / 8.81m, advance 15 m. and 1 formwork for the execution of the first phase of the tunnel lining

Tunnel form equipment Prado – Porto

Customer: UTE Prado-Porto (Vías, Torrescamara, Vimac)
Country: España
Location: Vilar de Barrio (Orense)
Year: 2015

Description:

Construction project for the new HSR called the North-Northwest Corridor. Built by the Ministry of Development through Adif Madrid-Galicia HSR. Puebla de Sanabria-Lubián-Ourense section. Prado-Porto sub-section, single high-speed international gauge track with maximum speeds of 350 km / h. Right track (9.1km.) And left track 1.6 km

IDENTIFIED NEEDS:
Self-supporting equipment consisting of 2 formwork and 2 transfer travelers, R = 4.38 / 8.81m, advance 15 m. and 1 formwork for the execution of the first phase of the tunnel lining

SEE WHAT ELSE WE’VE BEEN DOING


Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team understand which sections of the website you find most interesting and useful.