Maritime formwork Crown wall, Haifa Port
Customer: Shapir-ashtrom
Country: Israel
Location: Haifa Port
Year: 2018
Description:
Two teams worked simultaneously to make the first part of the crown wall formwork in different sections of the alignment. And once they had made a few minimums layings of the first phase, begin anchor simultaneously the formwork of the second phase on the section made.
IDENTIFIED NEEDS:
What was the challenge?:
What was the challenge?:
Mechanical automation of work modeMaritime formwork Crown wall, Haifa Port
Customer: Shapir-ashtrom
Country: Israel
Location: Haifa Port
Year: 2018
Description:
Two teams worked simultaneously to make the first part of the crown wall formwork in different sections of the alignment. And once they had made a few minimums layings of the first phase, begin anchor simultaneously the formwork of the second phase on the section made.
IDENTIFIED NEEDS:
What was the challenge?:
SEE WHAT ELSE WE’VE BEEN DOING
-
France
-
Philippines
-
Scotland
-
Reunion Island
-
Hong Kong
-
PORTUGAL