Maritime formwork Crown wall, Haifa Port
Customer: Shapir-ashtrom
Country: Israel
Location: Haifa Port
Year: 2018
Description:
Two teams worked simultaneously to make the first part of the crown wall formwork in different sections of the alignment. And once they had made a few minimums layings of the first phase, begin anchor simultaneously the formwork of the second phase on the section made.
IDENTIFIED NEEDS:
The optimization of the cycle times, with a system that allows a fast execution, improving the times and finishes of a standard or traditional formwork system.
What was the challenge?:
Deliver the material within the required period and achieve the required work cycles.
What was the challenge?:
Mechanical automation of work modeMaritime formwork Crown wall, Haifa Port
Customer: Shapir-ashtrom
Country: Israel
Location: Haifa Port
Year: 2018
Description:
Two teams worked simultaneously to make the first part of the crown wall formwork in different sections of the alignment. And once they had made a few minimums layings of the first phase, begin anchor simultaneously the formwork of the second phase on the section made.
IDENTIFIED NEEDS:
The optimization of the cycle times, with a system that allows a fast execution, improving the times and finishes of a standard or traditional formwork system.
What was the challenge?:
Deliver the material within the required period and achieve the required work cycles.