Maritime formwork Crown wall, Haifa Port

  Rubrica Maritime

Client: Shapir-ashtrom

Israel

Emplacement: Haifa Port
Année : 2018
FAITS MARQUANTS:
Formwork to execute in two phases, adapting in the second phase to the changes of geometry of the crown wall formwork along the alignment.
BESOINS IDENTIFIÉS:
The optimization of the cycle times, with a system that allows a fast execution, improving the times and finishes of a standard or traditional formwork system.

Quel était le défi?:
Deliver the material within the required period and achieve the required work cycles.

Rubrica Innovation:
Mechanical automation of work mode
Description:

Two teams worked simultaneously to make the first part of the crown wall formwork in different sections of the alignment. And once they had made a few minimums layings of the first phase, begin anchor simultaneously the formwork of the second phase on the section made.