The construction of the shoulder is now completed, with the innovative wave energy dissipation system, using blow-holes for this. The end result has been a success, achieving daily sections in order to adapt to the reduced time frame that the construction required.
* Maximum cart progress: 11 meters.
* Total length of construction: 450 meters.
* Volume of concrete in the maximum section: 420 m3.
* Cart features:
Hydraulic progress on rails.
Formwork and formwork removal system: Hydraulic.
Hydraulic supply.
It has a hydraulic control unit for operating all cylinders and progress engines.