UTE DIQUE ESTE WITH FCC AND BECSA, AT THE PORT OF CASTELLON

Nov 4, 2011 | Rubrica Maritime

The construction of the shoulder is now completed, with the innovative wave energy dissipation system, using blow-holes for this. The end result has been a success, achieving daily sections in order to adapt to the reduced time frame that the construction required.

* Maximum cart progress: 11 meters.
* Total length of construction: 450 meters.
* Volume of concrete in the maximum section: 420 m3.
* Cart features:
Hydraulic progress on rails.
Formwork and formwork removal system: Hydraulic.
Hydraulic supply.
It has a hydraulic control unit for operating all cylinders and progress engines.

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team understand which sections of the website you find most interesting and useful.