Last week, our engineers Paula Rinaudo and Juan Novoa, has been in Reunion Island giving assistance in the next points:
- Spreader beam is already assembly and onsite test are being done. Test on air, to check proper behavior of winches and hydraulic system were successfully done
- The structure was submerged and connected to the lifting structure on the pontoon. Lifting test was successfully done
- First operation is expected for the following days