Work progress capping beam in Haifa Port

The capping beam of the alignment Q8 in the port of Haifa is finally finished, in the alignment Q7 remains only the last segment to be poured and two of the formworks have been assembled to work simultaneously in the Q6 to speed up the construction of the same.

Progress Haifa capping beam

Amazing image of the special equipment of capping beam formwork (By RUBRICA MARITIME) together with the strap footings in a single concreting phase. Progress of 15.5 m and a production of one laying per week. RUBRICA MARITIME once again with an advanced solution of...